Case Studies

Results

Operational improvement measured in throughput, cost, time, and capability — not slide decks. A selection of representative engagements across industries and service areas.

25+Years of Experience
50+Engagements Delivered
12+Industries Served
$20M+Client Value Created
01
Lean / Six SigmaPAPER Manufacturing

Reducing Manufacturing Downtime Associated with Water Treatment Bottleneck

The Challenge

A mid-size paper manufacturer was struggling with chronic water treatment bottlenecks and downtime extensions in a high-cost production line. Wait times were unpredictable, overtime was endemic, and the root causes were poorly understood.

The Approach

Wheeler led a structured DMAIC project across all upstream and downstream processing lines. Data collection associated with downtime for water treatment was trended and improved. Samples taken provided direction for both mechanical and chemical treatment options.  After 3 iterations of improvements the associated downtime was completely eliminated.

Measured Results

100%Elimination of downtime for water treatment
61%Reduction in changeover duration
8%Increase in line utilization
$300KAnnualized cost avoidance
02
Industrial Engineering & CapExIndustrial Equipment Manufacturing

Greenfield Manufacturing Facility — On Time, Under Budget

The Challenge

A publicly traded industrial manufacturer needed to start up a new 23,000 sq ft facility within 8 months to meet delivery commitment and growth projections.

The Approach

Served as project manager from site take-over through commissioning. This included equipment specification, contractor management, material flow design, utility coordination, and workforce ramp-up planning. A rigorous stage-gate process kept scope, schedule, and budget under control throughout.

Measured Results

8 moFacility operational — on schedule
4%Under original capital budget
23KSquare feet commissioned
0Lost-time incidents during construction
03
CDMO & R&D Project ManagementBiotech CDMO

Technology Transfer and Capacity Step Change Driven by COVID-19

The Challenge

A biotech related operation needed to ramp volume of a complex process from a small operation to several CDMO operations, both domestic and abroad. The timeline was aggressive, the CDMO relationships were non-existent, and the team lacked bandwidth for technology transfer.

The Approach

Wheeler managed the full technology transfer project — from process characterization documentation through engineering runs and PPQ. A detailed progress register was maintained throughout, and weekly cross-functional reviews kept both the sponsor and CDMO aligned on critical path activities.

Measured Results

6 wkTo attain double capacity
100%Order fulfilment in 8 months
9New CDMO operations qualified globally
$8+ MAdditional EBITDA
04
ERP / MRP ImplementationELECTRONICS POLISHING

ERP Post Go-Live Support

The Challenge

A global consumables supplier to various polishing industries changed from legacy ERP to new SOX compliant software.  Within weeks, orders were late due to poor capacity and MRP planning.  Backlog had risen by over a million dollars and On-time delivery was cut in half.

The Approach

Wheeler led the charge to gain access to critical data inside the ERP leading to a better understanding of the software functionality. Materials Requirement Planning (MRP) quickly became the immediate focus because stock-outs were high. After understanding software functionality and cleaning data associated with capacity planning and MRP, On-Time delivery rose from 34% to the low 90's. Backlog value associated with customer request dates dropped from $1.2M to less than $50k.

Measured Results

95.8%Drop in late order value
0MRP related Stock-Outs
59%Jump in On-Time Delivery
40%Reduction in expediting activity
05
M&A IntegrationConsumer Products

Post-Acquisition Operational Integration Completed in 90 Days

The Challenge

A strategic acquirer needed to integrate a newly purchased consumer products manufacturer into its existing operations within a tight window to capture synergies and avoid customer disruption. The acquired facility had different processes, systems, and quality standards.

The Approach

Wheeler conducted a rapid operational due diligence in the first two weeks post-close, then developed and executed a 90-day integration plan covering production consolidation, quality system alignment, ERP data migration, and workforce transition. Daily stand-ups and a shared integration tracker kept all workstreams synchronized.

Measured Results

90 daysFull operational integration
$2.1MYear-one synergies captured
100%Customer orders fulfilled on time during transition
0Quality escapes during integration period
06
Training & EducationSpecialty Chemicals

Building a Sustainable CI Program from the Ground Up

The Challenge

A paper and non-wovens manufacturer had recognized the potential benefits of a formal Continuous Improvement (CI) program. Under the direction of Wheeler and other cross-functional SME consultants, a program needed to be launched, and measurable net gains had to be documented.

The Approach

Coordinated designed and delivered a 12-month capability-building program: Lean/Kaizen fundamentals training for all supervisors, a cohort of three internal practitioners, and a structured Kaizen event calendar with internal facilitation from month four onward. Coaching and facilitation was provided throughout and gains for specific projects far exceeded expectations of team members.

Measured Results

3Certified internal PKE's
8Active Kaizen events running simultaneously by year two
27%OEE improvement across targeted lines
3 yrSustained improvement trajectory post-engagement

All case studies represent actual engagement outcomes. Client names and identifying details have been omitted to preserve confidentiality. Results vary by engagement scope, organizational context, and implementation fidelity. Past results are not a guarantee of future performance.

Your results start
with a conversation.

Every engagement in this portfolio began with a direct conversation about a specific operational challenge. Let's have that conversation about yours.

Start a Conversation